Basingstoke Business Centre

Working in a busy, fully occupied business centre, Quaystone carried out the full refurbishment of the building envelopes; providing guaranteed weather-tightness and an improved appearance to 20 units.

Works included:-

  • Rooflight replacement
  • Replacement roof cladding and repair
  • Complete Giromax and Girosil roof coating including cut edge treatment
  • Aluminium window restoration with epoxy finish
  • Roller door restoration
  • Signage replacement
  • Minor external electrical works


Key features

  • Daily liaison with occupants and neighbours to maintain access and restrict noisy works
  • Providing safe site access whilst maintaining parking and public access
  • Complete external refurbishment of 20 occupied units

Client – CBRE

Value – Approx £350k

Contract – JCT Minor Wks

Duration – 16 Weeks

Completion – 01/04/2018