Bracknell Ambulance Station

Client:
Bracknell Ambulance Service
Value:
£320k
Contract:
N/A
Duration:
14 Weeks
This project was recently completed, a full designed, fast track project. The scheme was aimed at improving facilities and crew wellbeing.

This project was recently completed, a full designed, fast track project. The scheme was aimed at improving facilities and crew wellbeing.

The works involved.

  • Full electrical re-wire
  • New Crew & Kitchen Refurbishment
  • New Sluice Room Upgrades
  • New AC Systems
  • Re-surfacing warehouse coatings
  • New EV Charging Points
  • New Ceiling, Wall and floor finishes throughout.

Due to the ongoing operations that had to continue throughout the project, works were carefully planed and all electrical change overs programmed with such care that the requirement to prove a ups generator was negated. Welldone team!

The project was completed on time and in budget and furthermore improved the well being and working facilities of our valuable emergency care services!