Fleets Corner Industrial Estate, Poole

With heavy traffic through this busy industrial estate, the precast concrete duct covers had deteriorated badly.  Quaystone were engaged to replace them with continuous duct slabs using permanent shuttering, steel reinforcement and in-situ concrete.


Key features

  • Busy industrial estate with constant lorry traffic
  • Consultation with businesses on the estate
  • Coordinated road closures and traffic management
  • Fully engineered solution including rigorous quality testing (concrete cubes)
  • Maintenance of undamaged gas supply throughout
  • Risk assessed activities including protecting deep trenches

Client – CBRE

Value – Approx £40k

Contract – Minor Works

Duration – 13 Weeks

Completion – November 17