Unit 10-11 Walworth Industrial Estate, Basingstoke

Quaystone have completed the extensive internal and external refurbishment of these two units, in the heart of a busy industrial estate, ready for occupation by new tenants. Works included:-

  • Asbestos roof removal
  • Rooflight replacement
  • Replacement composite roof cladding and repair
  • Replacement gutter liners
  • Mechanical and electrical system upgrades
  • New cladding and flashings
  • New epoxy floor
  • Full internal redecoration including ceilings, flooring and painting


Key features

  • Daily liaison with neighbours to maintain access and restrict noisy works
  • Maintaining public access and parking
  • Protecting adjacent property during works
  • Warranty backed weatherproofing works to building envelope

Client – CBRE

Value – Approx £300k

Contract – JCT Minor Wks

Duration – 10 Weeks

Completion – 01/04/2018